    I have a MS Project Schedule which I believe is corrupt. I noticed there are Question Marks right next to a Task Name and was wondering if this could be the reason the file is corrupt. I am aware that it is ok for the Duration column to have Question Marks.

    Can someone shed some light on this and also what is the best way to recover a Schedule? I have tried using the Administrative Restore option which has worked once in the past on a previous schedule but it hasn't worked for this schedule. It restored the file but it was still corrupt with dates going back to Year 1949!!

     