Asked by:
Custom job properties - lost when copying a job?

Question
-
Hi all,
I make extensive use of custom job properties to store application framework data. However, when I copy a job in the cluster manager (2008R2 SP2), the custom properties are not copied. Is this a bug or a feature? Am I doing something wrong?
(It works well if I export the job to xml and then create a new job from the file. But that is just a workaround.)
Regards
Matthias
Monday, January 23, 2012 6:10 AM
All replies
-
Hi Matthias,
Thank you for reporting this issue. It was reproduced and added to our bug database.
Regards,
ŁukaszMonday, January 23, 2012 4:39 PM -
Hi Lukasz,
more than half a year has passed. Has this bug been fixed somehow?
Regards
Matthias
Tuesday, October 16, 2012 10:32 AM -
Hi Matthias,
This issue is fixed in HPC Pack 2012 Beta: http://blogs.technet.com/b/windowshpc/archive/2012/09/06/announcing-the-hpc-pack-2012-beta-program.aspx
Thanks,
ŁukaszTuesday, October 16, 2012 3:18 PM -
Hi Lukasz,
thanks for the fast reply.
Do I need to have Windows Server 2012 in order to run HPC Pack 2012?
Regards
Matthias
Wednesday, October 17, 2012 10:23 AM -
Hi Matthias,
Yes, Windows Server 2012 is required on the headnode and WCF broker nodes.
Regards,
ŁukaszWednesday, October 17, 2012 3:47 PM