Issue related to changing owner RRS feed

  • Question

  • hello everyone,

    i faced issue when i was restoring individual project. My scenario is:

    1. Full backup project to offline version
    2. Delete project from Draft+Publish and delete it's project site
    3. Open offline one and save to server

    after step3 i dont knew that my account was been project owner :( . A couple of day after that, truely owner ask me give his back owner permission, i was change owner and issue appeared: if member submit his task then it push to me (im not owner at this time). Im try to "manual" restore, Administrative Restore but both of them not work.

    anyone please explain to me what is going on

    many thank

    nguyễn dương phú

    Monday, August 27, 2012 5:10 PM

Answers

All replies

  • By default user created the task is status manager for the task

    To update new status manager new owner has to open the project plan and  republish it

    Request the new owner to open the project plan in Project Pro

    Insert the column status manager, new owner should be listed as status manager, if not update the same manually for all the tasks, you can select the cell and drag all the to the bottom.

    Save and publish the project

    Ref similar thread

    http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/22d9c8e9-cd99-466b-b994-51b18bad0507


    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn
    Please click Mark As Answer; if a post solves your problem or Vote As Helpful; if a post has been useful to you


    Monday, August 27, 2012 5:45 PM
  • ah ha, ok thank you verymuch. Change all Status Manager cell is solution
    Monday, August 27, 2012 5:59 PM