EPM2010 Beta2 - Setting up Resource Rates RRS feed

  • Question

  • Hi;

    Applies: Beta2

    When setting up resources in PWA, we only have the option of setting up the standard rate without effective dates. Also, we cannot setup other rate tables. Is this also the case in RTM?

    If so, is the setup of the resource best done in Project Pro as before?


    Regards, PJ Mistry (Email: pj@projectsolution.co.uk | Web: http://www.projectsolution.co.uk | Blog: http://microsoftepmsolution.com)
    Tuesday, April 20, 2010 8:25 PM

Answers

All replies

  • PJ:

    Little has changed between 2007 and 2010 when it comes to managing the enterprise resource pool. While the bulk editing and batch editing features in PWA can be useful on occassion, the Project Client is still the tool of choice of serious ERP manipulation.


    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG
    Wednesday, April 21, 2010 1:18 PM
  • Thanks Gary. Just wanted to double check! The users, as you may know, get confused where they should start adding/updating data if half is done in PWA and rest in Pro.

    Much appreciated.