locked
Deliverables in PWA 2010 RRS feed

  • Question

  • What are the use, in Project Pro 2010, tab Tasks, drop down list "Deliverable", of the two commands:

     - Sync Deliverables

     - Sync Dependencies

    How do they work,

    Thanks 

    Thursday, October 6, 2011 7:41 AM

Answers

  • The sync will retrieve the latest deliverable information stored in a SharePoint list
    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page
    Thursday, December 22, 2011 6:41 AM
  • WLID,

    Sorry to be almost 2 years with this, but I just ran across this thread!

    "Sync Deliverables" will make the SharePoint Deliverables list in the Project Workspace correspond to the defined deliverables in the PROVIDING project, names and dates. Not sure what happens to deliverables only defined in SharePoint, but think they might be deleted. So, in essence, this operation is "Project --> SharePoint".

    "Sync Dependencies", on the other hand, CHANGES the SELECTED dependent tasks in the CONSUMING project to "sync" with the dates in the PROVIDER project SharePoint list. Depending on the scheduling mode, different things happen. BTW, there is no "undo" for these two operations!

    A "Manual Schedule" dependent task will have Start/Finish dates changed to match the Deliverable dates, and the Duration re-calculated. You have an option to "respect the links", but the original duration is lost.  

    An "Auto-schedule"dependent  task will have a constraint added, depending on the relationship of the dependent task dates to the Deliverable dates, with the possibility of a Start OR Finish date changing. I'm just now in the process of working up a table that lists all the possibilities, and the resultant effect on a dependent task.

    I am working with MSP 2010, completely, no 2007

    Hope this helps, belaed as it is!

    JTC


    JAckson T. Cole, PMP, MCITP

    • Marked as answer by WLID1966 Tuesday, September 3, 2013 12:38 PM
    Tuesday, September 3, 2013 12:16 PM

All replies

  • Hi,

    Check out http://blogs.msdn.com/b/project/archive/2007/02/24/deliverables.aspx for more info on Deliverables. As far as I know they haven't changed since 2007.

    Hope this helps,


    Alex Burton
    www.epmsource.com | Twitter
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page
    Thursday, October 6, 2011 8:42 AM
  • Hi,

    I know the very principle of the deliverable feature, but my question was about the Sync options (Deliverables or Dependencies). For me, there is no sync anywhere, but I’m probably missing something.

    Thanks 

    Thursday, October 6, 2011 9:01 AM
  • The sync will retrieve the latest deliverable information stored in a SharePoint list
    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page
    Thursday, December 22, 2011 6:41 AM
  • WLID,

    Sorry to be almost 2 years with this, but I just ran across this thread!

    "Sync Deliverables" will make the SharePoint Deliverables list in the Project Workspace correspond to the defined deliverables in the PROVIDING project, names and dates. Not sure what happens to deliverables only defined in SharePoint, but think they might be deleted. So, in essence, this operation is "Project --> SharePoint".

    "Sync Dependencies", on the other hand, CHANGES the SELECTED dependent tasks in the CONSUMING project to "sync" with the dates in the PROVIDER project SharePoint list. Depending on the scheduling mode, different things happen. BTW, there is no "undo" for these two operations!

    A "Manual Schedule" dependent task will have Start/Finish dates changed to match the Deliverable dates, and the Duration re-calculated. You have an option to "respect the links", but the original duration is lost.  

    An "Auto-schedule"dependent  task will have a constraint added, depending on the relationship of the dependent task dates to the Deliverable dates, with the possibility of a Start OR Finish date changing. I'm just now in the process of working up a table that lists all the possibilities, and the resultant effect on a dependent task.

    I am working with MSP 2010, completely, no 2007

    Hope this helps, belaed as it is!

    JTC


    JAckson T. Cole, PMP, MCITP

    • Marked as answer by WLID1966 Tuesday, September 3, 2013 12:38 PM
    Tuesday, September 3, 2013 12:16 PM