Hello everyone,
I planned a project in Project Professional 2016 and published the plan afterwards to pwa. Important to note is that the plan was published a week after the actual project start date (project start date: 11/02/17, published 11/09/17). I now have the issue
that pwa creates resource assignments with different start/finish dates for tasks that were sheduled before the plan was published.
For example: I've created a tasks with a start and finish date of 11/02/17. After the plan was published today (11/09/17), pwa creates a resource assigment for the task on 03/08/18. However, if I take a look at the project plan on pwa, the correct dates
(11/02/17) are still displayed.
This behavior is the same for all tasks with a start or finish date within the last work week.
What is the issue here and how can I solve this?
Thank you in advance!