HOW to set project server 2010 "zone time" and "week begin on monday" RRS feed

  • Question

  • with project server 2010, i can't find where we can set "zone time" to defini the currency used

    and i wish the week begins on monday

    or we set it in sharepoint?

    Friday, September 2, 2011 1:32 PM

Answers

  • Hi,

    Connent to the PWA site and click Site Actions > Site Settings > Regional Settings - you can update the time zone and locale here.

    To change the currency used for Project Server, navigate to PWA > Server Settings > Additional Server Settings - set the currency here.

    TO change the week start day, navigate to PWA > Server Settings > Task Settings and Defaults - set the Week starts on here.

    Hope that helps

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Friday, September 2, 2011 1:37 PM

All replies

  • Hi,

    Connent to the PWA site and click Site Actions > Site Settings > Regional Settings - you can update the time zone and locale here.

    To change the currency used for Project Server, navigate to PWA > Server Settings > Additional Server Settings - set the currency here.

    TO change the week start day, navigate to PWA > Server Settings > Task Settings and Defaults - set the Week starts on here.

    Hope that helps

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com
    Friday, September 2, 2011 1:37 PM
  • thank you, it's very kind of you, BINGO that's done!
    Friday, September 2, 2011 1:48 PM