locked
Is it possible to manually trigger the job “Reporting (Resources Capacity Range Sync)” ? (Version 2007) RRS feed

  • Question

  • Hello,

    Resource Capacity settings are scheduled to be synched at 1AM (default setting), but the job never appears in the queue. In the reporting database, the resource capacity information is not available.

    Is it possible to start the sync-job (job “Reporting (Resources Capacity Range Sync)”) manually? Maybe the job is just nog triggered automatically at 1AM, or mayby the job is triggered but fails...

    Ideas?

    Thanks

    Wim 

    Thursday, June 16, 2011 9:49 AM

Answers

All replies

  • Hello Wim,

    You can trigger the job manually by backing any of the enterprise object & run the restore which will trigger the resource capacity Range sync job:

    Try this- step by step

    http://msfarmer.blogspot.com/2008/12/rebuild-project-server-reporting.html


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
    Thursday, June 16, 2011 11:14 AM
  • Hi Wim,

    Please try changing the scheduled time for the resource capacity job from 01:00 AM to 02:00 AM, this should recreate the Timer Job in central admin and the job should then fire automatically.

    Does this help?

    Thanks

    Paul


    Paul Mather
    Thursday, June 16, 2011 11:35 AM
  • Hello Amit,

     

    Your sollution worked!!

    I first tried the method proposed by Paul below, because it was easier tot do, but changing the scheduled time apparently was not enough.

     

    Thanks a lot
    Wim

    Thursday, June 16, 2011 3:52 PM
  • Hi Paul,

    As I mentioned already above to Amit, changing the scheduled time didn't solve the problem.

    Nevertheless, thanks for your advise!

    Regards
    Wim

    Thursday, June 16, 2011 3:54 PM
  • No problem Wim, my suggestion wouldn't have instantly populated the Resource Capacity details in the Reporting database but it should have fixed the issue with the job not running so the next time the job ran the data would have been available. I would check the queue history tomorrow if you altered the scheduled run time to see if it was successful tonight.

    Thanks

    Paul


    Paul Mather
    Thursday, June 16, 2011 6:00 PM