This forum has migrated to Microsoft Q&A. Visit Microsoft Q&A to post new questions.
Do you know how to setup the job template such that all the jobs submitted will be executed sequentially?
Thanks
Sam
Hi Sam,
What's your scenario? Why can't you run things in parallel?
Michael
Right now your best bet is to use an Activation Filter: http://technet.microsoft.com/en-us/library/dd346640(WS.10).aspx
This would allow your job to remain queued until your business logic determined it was ok to run (ie: it's predecessor reached a final state)...