locked
Cost rate tables on a resource assignment RRS feed

  • Question

  • 1) Is there any way I can change them within Project Server 2010 ?

    2) and using PSI?

    Many thanks

    Wednesday, April 17, 2013 2:31 AM

Answers

All replies

  • If I have understood you correctly, go to the resource sheet in PWA, and double click the resource. Then click the costs tab.

    Think that's what you mean...

    Wednesday, April 17, 2013 4:45 PM
  • thanks, but I mean changing it on the resource assigment and that would be different from changing it on the resource only. many thanks

    Wednesday, April 17, 2013 6:21 PM
  • Resource Usage view.  Insert Cost Rate Table field.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    Wednesday, April 17, 2013 7:29 PM
  • Sorry, could not find that on PWA. Could you exactly tell me how to get there?

    Thanks

    Thursday, April 18, 2013 2:42 PM
  • It is in Project Pro, not PWA.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    Thursday, April 18, 2013 2:44 PM
  • Ok, so there is no way of doing this with PWA/PS 2010 as my question says?

    Thanks

    Thursday, April 18, 2013 3:00 PM
  • Sorry for the misunderstanding, as your question mentioned Project Server, but not PWA specifically. There is no way in PWA. I can't answer your second question.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    Thursday, April 18, 2013 4:53 PM
  • Hi Andres,

    You can do this using Project Pro 2010. But using PWA, you will not be able to change the resource cost rate at project level. But, using PSI and little but of custom coding, you can do it.

    Please check following link for online SDK:

    http://msdn.microsoft.com/en-us/library/office/websvcresource_di_pj14mref(v=office.14).aspx


    Vikram Daruru - MSFT

    • Proposed as answer by Vikram Daruru Saturday, July 13, 2013 4:14 PM
    • Marked as answer by Vikram Daruru Wednesday, June 4, 2014 3:10 AM
    Saturday, July 13, 2013 4:07 PM