Resource capacity is 0h on the Resoure Availability report question RRS feed

  • Question

  • Hello,

    I can'y figure out why this resource capacity is 0h on the Resoure Availability report in Project Server.

    I checked the resource allocation and it is set to 75% under Server Settings. Does anyone know what can be causing this?

    Thank you

    Friday, March 30, 2012 1:12 PM

Answers

  • Can you go to Edit Resource and check if the Team Assignment Pool check box is selected fro this particular resource.


    Abhijeet M. Mohite

    • Marked as answer by pawel850 Friday, March 30, 2012 1:40 PM
    Friday, March 30, 2012 1:26 PM

All replies

  • From Resource Center> Resource Avaiability

    Friday, March 30, 2012 1:17 PM
  • Can you go to Edit Resource and check if the Team Assignment Pool check box is selected fro this particular resource.


    Abhijeet M. Mohite

    • Marked as answer by pawel850 Friday, March 30, 2012 1:40 PM
    Friday, March 30, 2012 1:26 PM
  • Thanks for help!
    Friday, March 30, 2012 1:40 PM
  • Good to know it helped you.

    Please click "Vote As Helpful" if it helped you.


    Abhijeet M. Mohite

    Friday, March 30, 2012 1:41 PM