Hi there,
Answer to your question is NO, as a best practice, every week project manager accepts the task updates and publishes the project plan. If you have schedule administrative backup of Project Plans
using PWA, which nothing but taking backup in archive database, all processed task updates will be backup. In case of plan corruption, one has to delete the project plan from draft and published database. Using administrative restore option restore the project
plan which will be available in draft database accessed via Project Pro. When restored project plan is published.
Only missing updates will be pending tasks approval before taking administrative backup.
Often archive project plan method is used to store completed project plan for quick reference in the future.
http://technet.microsoft.com/en-us/library/gg597607.aspx
Hrishi Deshpande – Senior Consultant DeltaBahn