Hi,
when I create a portfolio analysis I receive the following message: The role custom field selected is not set for any resources; therefore, timephased resource analysis will not be possible.
I have created an enterprise resource field and tied it to a lookup table. I also set this field for all work resources.
What am I missing?
Thanks for any advice in advance
John
John