The role custom field selected is not set for any resources; therefore, timephased resource analysis will not be possible. RRS feed

  • Question

  • Hi,

    when I create a portfolio analysis I receive the following message: The role custom field selected is not set for any resources; therefore, timephased resource analysis will not be possible.

    I have created an enterprise resource field and tied it to a lookup table. I also set this field for all work resources.

    What am I missing?

    Thanks for any advice in advance

    John


    John
    Wednesday, March 16, 2011 7:55 PM