  • Hi!

    Is possibile set automatic approval for task updates, but I can't set approval rules for timesheet: all fields for controls are for tasks.

    Resource Manager want set for each resource a timesheet manager, but they want approve only vacancy and set automatic approval rules for timesheet. It is possible?

    Thank's!

    Thursday, November 18, 2010 2:31 PM

Answers

  • Samantha --
     
    There is no way to set up Rules for the automatic approval of Timesheet submissions.  As you know already, Rules only apply to Task updates.  The only way to force automatic approval of Timesheet updates is for the Project Server administrator to set each resource as his/her own Timesheet approver.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, November 18, 2010 3:13 PM

All replies

  • Samantha --
     
    There is no way to set up Rules for the automatic approval of Timesheet submissions.  As you know already, Rules only apply to Task updates.  The only way to force automatic approval of Timesheet updates is for the Project Server administrator to set each resource as his/her own Timesheet approver.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, November 18, 2010 3:13 PM
  • Thank's Dale :(