  • Question

  • We are looking at providing our mid-level supervisors data on how their reports are performing on assigned tasks by showing the number of tasks an individual completes early, on time and late each week.  We want to calculate off the scheduled finish, not the baseline finish so the variance fields are not an option.  Problem is, scheduled finish moves to the actual finish when a task is completed (we are using 2010).

    We've considered setting one of the baseline fields each Monday to capture finish dates for the week but with 70 something projects on the server, that isn't feasable to do each week.  Possibly a custom field and SSRS option would work?

    Any suggestions would be greatly appreciated.

     