Hi Simon,
my knowledge is the same as Badal's.
I solved that with an event driven VBA macro filling 11 custom fields on project level
(zzBP00-zzBP10). It looks like this:
Private Sub Project_BeforeSave(ByVal pj As Project)
....
ActiveProject.ProjectSummaryTask.zzBP00 = ""
ActiveProject.ProjectSummaryTask.zzBP01 = ""
....
If IsDate(ActiveProject.BaselineSavedDate(pjBaseline)) Then
ActiveProject.ProjectSummaryTask.zzBP00 =
ActiveProject.BaselineSavedDate(pjBaseline)
End If
If IsDate(ActiveProject.BaselineSavedDate(pjBaseline1)) Then
ActiveProject.ProjectSummaryTask.zzBP01 =
ActiveProject.BaselineSavedDate(pjBaseline1)
End If
...
End Sub
Perhaps that will give you an idea how to deal with?
Good luck!
Regards
Barbara