  • Question

  • Can anyone tell me where the 'Baseline create' time/date stamp exists in the reporting server (if it does).
    Tuesday, July 27, 2010 1:16 AM

Answers

  • Hi Simon,

    my knowledge is the same as Badal's.

    I solved that with an event driven VBA macro filling 11 custom fields on project level
    (zzBP00-zzBP10). It looks like this:

    Private Sub Project_BeforeSave(ByVal pj As Project)
    ....
    ActiveProject.ProjectSummaryTask.zzBP00 = ""
    ActiveProject.ProjectSummaryTask.zzBP01 = ""
    ....

     If IsDate(ActiveProject.BaselineSavedDate(pjBaseline)) Then
        ActiveProject.ProjectSummaryTask.zzBP00 =
    ActiveProject.BaselineSavedDate(pjBaseline)
     End If
     If IsDate(ActiveProject.BaselineSavedDate(pjBaseline1)) Then
         ActiveProject.ProjectSummaryTask.zzBP01 =
    ActiveProject.BaselineSavedDate(pjBaseline1)
     End If
    ...
    End Sub

    Perhaps that will give you an idea how to deal with?
    Good luck!

    Regards
    Barbara

    Tuesday, July 27, 2010 9:49 AM

All replies

  • Hi Simon Newton,

    As per my knowledge, It never goes into table, It goes into respective views therefore, check in Project and Task User View.

    Hope this helps you.

     

     


    Regards Badal Ratra
    • Proposed as answer by Badal Ratra Tuesday, July 27, 2010 8:55 AM
    Tuesday, July 27, 2010 8:55 AM
  • Hi Simon,

    my knowledge is the same as Badal's.

    I solved that with an event driven VBA macro filling 11 custom fields on project level
    (zzBP00-zzBP10). It looks like this:

    Private Sub Project_BeforeSave(ByVal pj As Project)
    ....
    ActiveProject.ProjectSummaryTask.zzBP00 = ""
    ActiveProject.ProjectSummaryTask.zzBP01 = ""
    ....

     If IsDate(ActiveProject.BaselineSavedDate(pjBaseline)) Then
        ActiveProject.ProjectSummaryTask.zzBP00 =
    ActiveProject.BaselineSavedDate(pjBaseline)
     End If
     If IsDate(ActiveProject.BaselineSavedDate(pjBaseline1)) Then
         ActiveProject.ProjectSummaryTask.zzBP01 =
    ActiveProject.BaselineSavedDate(pjBaseline1)
     End If
    ...
    End Sub

    Perhaps that will give you an idea how to deal with?
    Good luck!

    Regards
    Barbara

    Tuesday, July 27, 2010 9:49 AM