    We are using Project Server 2010 and We have 20 projects in Microsoft Project Server. But Single Entry Mode is not working for 2 project. There is no any error message in queue list and ULS logs.

    Does anybody knows these problem. Thanks

    Mehmet Kurt

     

    Friday, April 8, 2011 11:00 AM

Answers

All replies

  • Hi Mehmet

    This sounds somewhat strange. Care to share the behaviour you found for these 2 projects? Any change these projects were using % Complete as a progress reporting method before switching on single-entry mode? If yes I would suggest you re-publish these projects first. I did read something somewhere that there are known issue/s in Project Server 2010 if you switch single-entry mode on after you have been using a different progress reporting method before. I will search a bit for this and post back if I find it.

    Regards

    Coenraad Swanepoel

    Friday, April 8, 2011 12:33 PM
  • We are using Project Server 2010  as a Single Entry Mode Checked from that installed server and Actually There were no any error about single entry mode for these 2 project. Someday , We have realized the entry mode problem on Project Server with on Project Status Reports. There are 700 hours Timesheet Entry For the project but there are 550 hours actual work in Project  and Project Manager can be able to Approve Timesheet Task Detail. There is no any error in Queue List. I do not know What is the problem ?

    After 2 weeks, Same problem occurs on another project and another project have no problem except this.

     I am waiting for your reply Thank You.

    Regards

    Mehmet

     

    Friday, April 8, 2011 12:47 PM
  • Are you accepting all updates? Publishing all changes?
    Gary Chefetz, MCITP, MCP, MVP msProjectExperts