locked
Task timesheet locked due to failure to work RRS feed

  • Question

  • Is not possible enter time in the timesheet for all the tasks of one project and for all the resouces of this project. For some resources when time is enter an error occurs and for others the task of this project is locked at the timesheet.

    The error is:

    Timesheet:
    TimesheetFutureReportingNotAllowed (3206). Detalhes: id='3206' name='TimesheetFutureReportingNotAllowed' uid='caef9ec7-14bf-44f6-ac1f-5eec5bd0ecab'.
    Queue:
    GeneralQueueJobFailed (26000) - TimesheetUpdate.UpdateTimesheetMessage. Detalhes: id='26000' name='GeneralQueueJobFailed' uid='2df08a64-c8ac-4cc5-b909-2d7e115931ae' JobUID='65c5ebe3-41f9-4986-acbc-cbb560490ac6' ComputerName='EPMSERVER' GroupType='TimesheetUpdate' MessageType='UpdateTimesheetMessage' MessageId='1' Stage=''. Para obter detalhes, verifique os logs ULS no computador EPMSERVER para ver as entradas com JobUID 65c5ebe3-41f9-4986-acbc-cbb560490ac6.

     

    I am using EPM 2010 and Single Mode Entry.

    Thank you very much!

    Marina

    Friday, December 2, 2011 12:31 PM

Answers

  • You have a project server configuration that prohibits entering future time.  Remove this and try it.

    This is found in the Timesheet Settings and Defaults.

    The check the Allow Future Time Reporting.

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
    Friday, December 2, 2011 10:09 PM

All replies

  • You have a project server configuration that prohibits entering future time.  Remove this and try it.

    This is found in the Timesheet Settings and Defaults.

    The check the Allow Future Time Reporting.

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
    Friday, December 2, 2011 10:09 PM
  • Thank you very much.

    It works.

    Thursday, January 5, 2012 11:23 AM