Unable to Change Project Start Date in Project Server 2013 RRS feed

  • Question

  • Dear All,

    I have created new EPT in Project Server 2013. After that, when i am creating any new project in PWA 2013 by using newly created EPT, then i am not able to change Date as per my requirement. 

    Basically, EPT created on 02/18/2015 & even though i am changing Project start date then its again showing same date (02/18/2015)

    Kindly suggest what i can do.

    Wednesday, February 18, 2015 4:07 PM

Answers

  • Dear All,

    I got solution as whenever creating new EPT, all task should be Auto mode in Project Pro. If we have task in Manual mode in Project Pro then we will face such challenges.

    Tuesday, March 31, 2015 9:14 AM

All replies

  • Hello,

    Does this new EPT have a project plan template associated? What happens if you set the EPT not to have a plan template then create a new project from this EPT? Does that let you update the start date? The start date should default to today (date the project plan was created). If that works as expected, add the plan template back to the EPT (if you had one to start with) and test creating another project to see if that then works or you then get the same behaviour. This will point us to the cause hopefully. Do other EPTs work as expected?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    • Proposed as answer by Sriram E Wednesday, February 18, 2015 11:14 PM
    Wednesday, February 18, 2015 8:39 PM
  • Dear Paul,

    Today itself, i have created 5 new EPT associated with project plan template. For rest 4 EPT, all are working properly. I agree that when creating new project then start date in Project Details page takes by default today's date  but when changing it, then it is not reflecting that date (which we want).

    Wednesday, February 18, 2015 9:19 PM
  • So for the EPT that is not working as expected, remove the plan template and create a new test project, can you move the start date then?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Wednesday, February 18, 2015 9:24 PM
  • Yes, after removing Project plan template, i can change start date.
    Wednesday, February 18, 2015 9:27 PM
  • OK, so what is different with this plan template and the other plan templates you are successfully using on the other EPTs? Can you create a test plan template, associated it with the EPT and test again?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Wednesday, February 18, 2015 9:29 PM
  • I created test plan & then linked to EPT. But again same issue as i cant change date whereas if EPT is without any plan template then changes are happening.

    Is that i am missing some process?

    Thursday, February 19, 2015 5:38 AM
  • Does this issue have anything to do with the fact that the "Default" EPT cannot have a project plan template associated with it? Reading through the thread here creating new EPTs with Project Plan Templates associated with them it is possible to edit the Start Date but the pre-existing EPT cannot have its start date changed.


    Dominic Moss | MAPM Microsoft Certified Technology Specialist | Our Newsletter: PM News Project Server Specialists Project Server PRIME | Twitter: @Twitter | Facebook: @Facebook | Linkedin: Wellingtone

    Monday, February 23, 2015 4:27 PM
  • Dear All,

    I got solution as whenever creating new EPT, all task should be Auto mode in Project Pro. If we have task in Manual mode in Project Pro then we will face such challenges.

    Tuesday, March 31, 2015 9:14 AM
  • Hello ,

    i have faced the same where i can not change the start date in Project information PDP as it keeps the current date and ignore my changes (setting new start date in the past) , while i can change the project start date in Project Professional without any problem and it reflects correctly in PWA , i have also tried to create a new EPT without any project plan associated and still facing this issue while there is not project plan associated with the EPT

    still can not change project start date in PWA while i can change it Project Professional. 

    any ideas

    Thank you

     

    Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark As Answer

    Tuesday, May 12, 2015 3:27 PM
  • Dear Karim,

    Kindly keep Task Mode "AUTO" & try if it works. That i did & worked for me

    Friday, June 19, 2015 9:20 AM
  • Hi Vrij007, is your template scheduling from the FINISH date, rather than the start?

    Ben Howard [MVP] | web | blog | book | P2O

    Friday, June 19, 2015 11:07 AM