  • Hi,

    In a timesheet, I added a Personal Task : Insert Row > Insert Personal Task : Line Classification: "Training".

    I clicked Send Status and then I went in the Approval Center : the project tasks were there but the personal task was not.

    Personal Tasks don't need approval?

    Thanks

    Wednesday, February 23, 2011 4:52 PM

Answers

  • Hi,

    a personal task is as it is named. Since it is personal and there is no status manager for tasks created in this way,  there is no approval required.

    Regards
    Barbara