Hi,
I m working on Project Server 2007. Sometimes I have to add new task in the middle of preplanned task but doing so I have to change the date of other affected tasks. Is there any way that if I add a new task then the other affected tasks' date change
automatically. I have to do these things using PWA Site not Project Professional.
Thanks in advance.