What is Top level time reporting in PS 2010? RRS feed

  • Question

  • In PS 2010--->Server Settings--> Timesheet settings and Defaults--> Top level time reporting

    How does that helps?? any idea...

    Thanks ..

    Parag

    Thursday, July 8, 2010 5:43 AM

Answers

  • Many companies do not track resource hours by task, but rather by project,
    i.e. as a consultant on a project, I treat the project like one big bucket
    of hours. Allowing top level reporting allows resources to book hours against
    the top level summary task - not requiring them to book hours against a specific
    sub task.
     
    Does that help?
     
     
    - Andrew Lavinsky
     
     
    Thursday, July 8, 2010 10:43 AM