Microsoft Project

    Question

  • So I have just gotten Microsoft project and have much experience using this software, however I don't have very much experience with getting started or setting it up.

    With this being said, I set up my times to 6:30 am to 12:00 pm and 12:30 pm to 5:00 pm working 10 hours a day and 40 hours a week.

    However when I go to set a duration, example 1 day, it shows up on the bar as about 1.5 days duration, how do I fix this to show exactly 1 day?

    Tuesday, January 17, 2017 5:23 PM

Answers