project server 2010: creating or setting a baseline using PSI RRS feed

  • Question

  • Hi,

    I need to set (create) a baseline programmatically for a certain project. Can anyone post a sample code or a link to a sample code as I wasn't able to find any even in the SDK.

    Thanks,
    George

    Wednesday, February 9, 2011 8:43 AM

Answers

All replies

  • Hi George,

    The PSI does not contain a method to create or set a baseline. In order to baseline you will need to use the Project client. 

    I agree though, the inclusion of this feature would be a fantastic addition.

    Hope this helps,

     


    Alex Burton
    www.epmsource.com | Twitter
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page
    Wednesday, February 9, 2011 8:48 AM
  • Thanks Alexandar. In case we create a baseline using the project client, is there a way to edit this baseline (change the work hours for example) through the PSI because I have seen some attributes related to the baseline but no real explanation as to what they are or what they do.