MS Project 2010 signals error, when one task has linked more than one deliverable. RRS feed

  • Question

  • Strongely bizarre. I get the following message:

    Error

    The task you are attempting to link to already has a deliverable or dependency linked to it.
    Any idea what's up? In documentation I don't observe limitations in this field.
    Regards
    bp

    Bartosz
    Thursday, November 17, 2011 10:57 AM

Answers

All replies

  • Hi Bartosz,

    If you link deliverables to a task , you are limited to one deliverable per task. See Ben's post under the limitations section:
    http://www.applepark.co.uk/deliverables/


    though I haven't seen it on documentation (link below) but when we try to create a new deliverable on a task which already has one, it throws message which you mentioned.
    http://office.microsoft.com/en-us/project-server-help/create-and-manage-project-deliverables-HA010113059.aspx


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
    • Proposed as answer by Brian Kennemer, MVP Thursday, November 17, 2011 5:02 PM
    • Marked as answer by Hans.H Wednesday, November 30, 2011 10:55 PM
    Thursday, November 17, 2011 11:22 AM
  • Amit;

     

    I manage to link several deliverables to one task from the code (C#, PSI). In documentation on WebSvcOLP there's that You can link as many, as it takes. Problem starts in Project Professional, which for such a tasksystem shows the message.

     

    Regards

    bp


    Bartosz
    Thursday, November 17, 2011 11:30 AM