MS Project - XML Format 2013 doesn't work for 2019 RRS feed

  • Question

  • Hello, I have created a XML file to import to MS Project 2019. It works for version 2013 but doesn't for 2019, what is the problem with it? I followed all specifications on https://docs.microsoft.com/en-us/office-project/xml-data-interchange/introduction-to-project-xml-data to create it.

    Here is the screenshot for version 2013, screenshot for version 2019 and the XML file.

    Thank you!


    XML File: https://www.dropbox.com/s/ks9gbny1zcg6aua/Launch%20SaaS%20Product.xml?dl=0

    Monday, September 28, 2020 10:29 PM

Answers

  • fabiojpoli,

    Despite the guidance document you referenced, the standard duration mask for Project-specific xml files (at least all that I've looked at lately) uses ONLY Hours, Minutes, and Seconds.  I'd suggest you adopt something similar in your xml generator.  E.g. for the "Install Apache" task, pass a duration value of PT72H0M0S (72 hours, 0 mins, 0 sec), not P3DT0H0M0S.  (Do the same with work fields).  Unlike day/month/year values, such hour/minute/second values can be saved directly without external references.  Good luck, tom 


    • Marked as answer by fabiojpoli Monday, October 19, 2020 6:12 PM
    Tuesday, September 29, 2020 5:45 PM
  • Fixed the problem.

    To work is required to add the field "RemainingDuration" to the tasks and (as suggested by Tom) change the format to hours from days to hours. Even microsoft doc suppose to format duration like P2DT1H0M for 2 days 1 hour but the correct they support is only in days PT25H0M for 2 days and 1 hour.

    Thank you!

    • Marked as answer by fabiojpoli Monday, October 19, 2020 6:12 PM
    Monday, October 19, 2020 6:12 PM

All replies

  • fabiojoli,

    I'm a little confused. It looks like you have the Project file in 2013 and Project 2019, so what exactly are you trying to do?

    I didn't examine the XML but if you want to see the difference, why not save both Project files as XML and then do a line-by-line compare of the two XMLs.

    John

    Tuesday, September 29, 2020 12:00 AM
  • fabiojpoli,

    Despite the guidance document you referenced, the standard duration mask for Project-specific xml files (at least all that I've looked at lately) uses ONLY Hours, Minutes, and Seconds.  I'd suggest you adopt something similar in your xml generator.  E.g. for the "Install Apache" task, pass a duration value of PT72H0M0S (72 hours, 0 mins, 0 sec), not P3DT0H0M0S.  (Do the same with work fields).  Unlike day/month/year values, such hour/minute/second values can be saved directly without external references.  Good luck, tom 


    • Marked as answer by fabiojpoli Monday, October 19, 2020 6:12 PM
    Tuesday, September 29, 2020 5:45 PM
  • Hi Tom, thanks for your answer. I changed to hours only format and I still have problems. Here is my XML, there MS Project and also and image how I expected to be the gantt. There are many problems with dates, many dates are wrong and on XML the dates are correct, what I am missing?

    Thank you!

    XML: https://pastebin.com/TFjMsxAq

    MS Project 2019:

    Wrong dates

    Expected:
    Expected

    
    
    
    

    
    
    
    
    • Edited by fabiojpoli Wednesday, October 14, 2020 7:21 PM
    Wednesday, October 14, 2020 7:11 PM
  • Hi John, I posted the 2013 showing that it is working fine, but for 2019 it doesnt. Please look my last answer here, I have fixed some things but still some problems with dates only.

    I can't compare because I dont have the XML file for Project 2019, because it doesnt work. Understand that I am creating the XML by myself, I am not creating the project using MS Project, I am creating XML using javascript.

    Thank you
    
    
    
    
    Wednesday, October 14, 2020 7:14 PM
  • fabiojpoli,

    I'm still confused as to exactly what you are trying to accomplish. You have the Project 2013 file, you have the Project 2019 file, so why do you need an XML?

    You say you don't have the XML for Project 2019 because it "doesn't work". How exactly does it "not work"?

    Are you able to share both the Project 2013 and Project 2019 files? If so, can you post them to a readily accessible link or you can send them to me via e-mail.

    John

    Wednesday, October 14, 2020 8:32 PM
  • fabiojpoli,

    I'm still confused as to exactly what you are trying to accomplish. You have the Project 2013 file, you have the Project 2019 file, so why do you need an XML?

    You say you don't have the XML for Project 2019 because it "doesn't work". How exactly does it "not work"?

    Are you able to share both the Project 2013 and Project 2019 files? If so, can you post them to a readily accessible link or you can send them to me via e-mail.

    John

    John,

    I have one single XML file, here is it readable: https://pastebin.com/TFjMsxAq

    This XML was created with Javascript. It worked for version 2013 but not for version 2019. I need to change the XML to work for version 2019 with data shown exactly like this:

    
    
    
    
    Wednesday, October 14, 2020 9:24 PM
  • John,  As I understand it, fabiojpoli has coded up something in javascript to transfer some known schedule data from another source into a form (i.e. xml) that can be imported into Project.  His original images showed the results of importing this xml into MSP 2013 and MSP 2019, respectively, from which he interpreted that his xml was correct for the former but not the latter.

    fabiojpoli,  After another look, it just seems that you've gone further away from what's expected by the program - even if your original xml had been correctly imported by MSP 2013, I doubt the new one would.  It might be overkill, but I'd just correct the schedule in MSP 2019, export to xml, then compare the new xml to what you've got.  The exported file I came up with is about 4x the size of yours; while much of that extra data is superfluous, the devil is in the details.  (It looks like you've added some new fields in this latest version, including some resource calendar references that are incorrect and causing other issues.)

    This is a pretty esoteric subject.  Good luck, tom   

    Wednesday, October 14, 2020 9:27 PM
  • fabiojpoli,

    I must be missing something. If you have your file in Project 2013, opened from an XML, and it's correct, why not just open that file in Project 2019. Are you saying that for some reason you need to create additional schedules using javascript created XML and need to get them into Project 2019? If so, I'd go with Tom's suggestion except I don't see a need for going through the process of "correcting" the XML generated Project 2019 file, just open the Project 2013 file in Project 2019, save that to XML and then compare XML format.

    John

    Wednesday, October 14, 2020 9:50 PM
  • Are you saying that for some reason you need to create additional schedules using javascript created XML and need to get them into Project 2019?

    John

    Hi John, no. I am creating the whole XML file manually using Javascript. Thank for your suggestions, I will try open my xml to version 2013 what is working, save the project and then try open the project file (not XML) on version 2019 then still on version 2019 export the project to XML format and compare with my XML file, another try also will be simply import my XML to 2013 and save, after save, on version 2013, export to XML and compare that XML with mine generated by javascript. If you have any other suggestion please let me know. Thank you so much!
    
    
    
    
    Thursday, October 15, 2020 11:44 AM
  • John,  As I understand it, fabiojpoli has coded up something in javascript to transfer some known schedule data from another source into a form (i.e. xml) that can be imported into Project.  His original images showed the results of importing this xml into MSP 2013 and MSP 2019, respectively, from which he interpreted that his xml was correct for the former but not the latter.

    fabiojpoli,  After another look, it just seems that you've gone further away from what's expected by the program - even if your original xml had been correctly imported by MSP 2013, I doubt the new one would.  It might be overkill, but I'd just correct the schedule in MSP 2019, export to xml, then compare the new xml to what you've got.  The exported file I came up with is about 4x the size of yours; while much of that extra data is superfluous, the devil is in the details.  (It looks like you've added some new fields in this latest version, including some resource calendar references that are incorrect and causing other issues.)

    This is a pretty esoteric subject.  Good luck, tom   

    Thanks Tom for perfect clarification to John.

    Also Thank for your suggestions, I will try open my xml to version 2013 what is working, save the project and then try open the project file (not XML) on version 2019 then still on version 2019 export the project to XML format and compare with my XML file, another try also will be simply import my XML to 2013 and save, after save, on version 2013, export to XML and compare that XML with mine generated by javascript. If you have any other suggestion please let me know.

    About the calendar if I remove CalendarUID from task it break and also put PercentWorkComplete to assignments 
    result is a messy. I am based in a XML demo from MS Project demo projects but is not helping because data are very different. That documentation is really very confuse. I also tried to change data on MS Project 2019 after import but then it cause more and more messy because data are related.

    I also tried but less data (4 records) and it works, but not for many data like what I posted.

    Thank you so much!

    
    
    
    


    
    
    
    
    • Edited by fabiojpoli Thursday, October 15, 2020 11:52 AM
    Thursday, October 15, 2020 11:50 AM
  • fabiojpoli,

    Once again, the devil is in the details....  Your xml incorrectly assigns base calendars directly to resources.  Unique resource calendars need to be directly added (with name, UID, BaseCalendarUID, etc.) to the calendars collection; then only resource calendars can be assigned to the resources.  There are likely other issues.  XML data transfer between Project and other scheduling tools has always been troublesome.  Sorry I can't help further.  Good luck, tom

    Thursday, October 15, 2020 3:01 PM
  • fabiojpoli,

    Sorry, I don't have any other suggestions. The only time I use XML is to help clear corruption from Project files so my experience is very limited.

    John

    Thursday, October 15, 2020 5:51 PM
  • I have fixed many things, now problems I have only on duration, start and finish dates and only for specific records. I dont understand why, because my XML is correct. In yellow are wrong values and bellow the tasks on XML with the correct values and the whole XML. What is the problem?

    Whole XML: https://pastebin.com/unXyugLZ

    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P1M17DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-03-20T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P1M17DT0H0M0S</ManualDuration>
        <ManualFinish>2019-03-20T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Launch SaaS Product</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>1</OutlineLevel>
        <OutlineNumber>1</OutlineNumber>
        <PercentComplete>34</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>1000</UID>
        <WBS>1</WBS>
        <Work>P5M13DT16H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-23T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>PT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-23T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Setup web server</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>2</OutlineLevel>
        <OutlineNumber>1.1</OutlineNumber>
        <PercentComplete>42</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>1</UID>
        <WBS>1.1</WBS>
        <Work>PT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P3DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-17T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P3DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-17T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Install Apache</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.1.1</OutlineNumber>
        <PercentComplete>50</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>11</UID>
        <WBS>1.1.1</WBS>
        <Work>P3DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P3DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-17T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P3DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-17T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Configure firewall</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.1.2</OutlineNumber>
        <PercentComplete>50</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>12</UID>
        <WBS>1.1.2</WBS>
        <Work>P3DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P3DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-17T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P3DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-17T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Setup load balancer</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.1.3</OutlineNumber>
        <PercentComplete>50</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>13</UID>
        <WBS>1.1.3</WBS>
        <Work>P11DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P2DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-16T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P2DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-16T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Configure ports</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.1.4</OutlineNumber>
        <PercentComplete>50</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>14</UID>
        <WBS>1.1.4</WBS>
        <Work>P2DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P2DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-23T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P2DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-23T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Run tests</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.1.5</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>14</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>13</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>12</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>28800</LinkLag>
            <PredecessorUID>11</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>15</UID>
        <WBS>1.1.5</WBS>
        <Work>P2DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P15DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-13T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P15DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-13T00:00:00</ManualFinish>
        <ManualStart>2019-01-23T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Website Design</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>2</OutlineLevel>
        <OutlineNumber>1.2</OutlineNumber>
        <PercentComplete>34</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-01-23T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>2</UID>
        <WBS>1.2</WBS>
        <Work>P16DT16H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P5DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-30T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P5DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-30T00:00:00</ManualFinish>
        <ManualStart>2019-01-23T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Contact designers</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.2.1</OutlineNumber>
        <PercentComplete>70</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>15</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-01-23T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>21</UID>
        <WBS>1.2.1</WBS>
        <Work>P6DT16H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P1DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-31T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P1DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-31T00:00:00</ManualFinish>
        <ManualStart>2019-01-30T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Create shortlist of three designers</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.2.2</OutlineNumber>
        <PercentComplete>60</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>21</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-01-30T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>22</UID>
        <WBS>1.2.2</WBS>
        <Work>P1DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P2DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P2DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-01-31T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Select &amp; review final design</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.2.3</OutlineNumber>
        <PercentComplete>50</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>22</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-01-31T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>23</UID>
        <WBS>1.2.3</WBS>
        <Work>P2DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>PT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-02-02T00:00:00</ManualStart>
        <Milestone>1</Milestone>
        <Name>Inform management about decision</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.2.4</OutlineNumber>
        <PercentComplete>100</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>23</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-02-02T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>24</UID>
        <WBS>1.2.4</WBS>
        <Work>PT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-13T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>PT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-13T00:00:00</ManualFinish>
        <ManualStart>2019-02-04T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Apply design to web site</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.2.5</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>24</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>1</Rollup>
        <Start>2019-02-04T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>25</UID>
        <WBS>1.2.5</WBS>
        <Work>PT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P15DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P15DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Setup Test Strategy</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>2</OutlineLevel>
        <OutlineNumber>1.3</OutlineNumber>
        <PercentComplete>15</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>3</UID>
        <WBS>1.3</WBS>
        <Work>P1M1DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P5DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-19T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P5DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-19T00:00:00</ManualFinish>
        <ManualStart>2019-01-14T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Hire QA staff</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.3.1</OutlineNumber>
        <PercentComplete>40</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-01-14T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>31</UID>
        <WBS>1.3.1</WBS>
        <Work>P5DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P10DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P10DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Write test specs</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.3.2</OutlineNumber>
        <PercentComplete>10</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>33</UID>
        <WBS>1.3.2</WBS>
        <Work>P26DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P10DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P10DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Unit tests</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.3.2.1</OutlineNumber>
        <PercentComplete>20</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>31</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>331</UID>
        <WBS>1.3.2.1</WBS>
        <Work>P10DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P5DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-26T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P5DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-26T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>UI unit tests / individual screens</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.3.2.2</OutlineNumber>
        <PercentComplete>10</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>31</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>332</UID>
        <WBS>1.3.2.2</WBS>
        <Work>P5DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P10DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P10DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Application tests</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.3.2.3</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>31</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>333</UID>
        <WBS>1.3.2.3</WBS>
        <Work>P10DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P1DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-01-22T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P1DT0H0M0S</ManualDuration>
        <ManualFinish>2019-01-22T00:00:00</ManualFinish>
        <ManualStart>2019-01-21T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Monkey tests</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.3.2.4</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>31</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-01-21T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>334</UID>
        <WBS>1.3.2.4</WBS>
        <Work>P1DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P1M2DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-03-20T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P1M2DT0H0M0S</ManualDuration>
        <ManualFinish>2019-03-20T00:00:00</ManualFinish>
        <ManualStart>2019-02-02T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Application Implementation</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>2</OutlineLevel>
        <OutlineNumber>1.4</OutlineNumber>
        <PercentComplete>39</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>3</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-02-02T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>4</UID>
        <WBS>1.4</WBS>
        <Work>P3M5DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-13T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>PT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-13T00:00:00</ManualFinish>
        <ManualStart>2019-02-02T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Phase #1</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>3</OutlineLevel>
        <OutlineNumber>1.4.1</OutlineNumber>
        <PercentComplete>47</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-02-02T00:00:00</Start>
        <Summary>1</Summary>
        <Type>1</Type>
        <UID>400</UID>
        <WBS>1.4.1</WBS>
        <Work>P17DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P5DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-09T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P5DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-09T00:00:00</ManualFinish>
        <ManualStart>2019-02-04T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Authentication module</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.1</OutlineNumber>
        <PercentComplete>100</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-02-04T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>41</UID>
        <WBS>1.4.1.1</WBS>
        <Work>P5DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P3DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-07T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P3DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-07T00:00:00</ManualFinish>
        <ManualStart>2019-02-04T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Single sign on</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.2</OutlineNumber>
        <PercentComplete>100</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-02-04T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>42</UID>
        <WBS>1.4.1.2</WBS>
        <Work>P3DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P4DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-08T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P4DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-08T00:00:00</ManualFinish>
        <ManualStart>2019-02-04T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Implement role based access</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.3</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-02-04T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>43</UID>
        <WBS>1.4.1.3</WBS>
        <Work>P4DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P3DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-07T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P3DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-07T00:00:00</ManualFinish>
        <ManualStart>2019-02-04T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Basic test coverage</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.4</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <Rollup>0</Rollup>
        <Start>2019-02-04T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>44</UID>
        <WBS>1.4.1.4</WBS>
        <Work>P3DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>P2DT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-13T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>P2DT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-13T00:00:00</ManualFinish>
        <ManualStart>2019-02-11T00:00:00</ManualStart>
        <Milestone>0</Milestone>
        <Name>Verify high test coverage</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.5</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>44</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>43</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>42</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <PredecessorLink>
            <LagFormat>7</LagFormat>
            <LinkLag>0</LinkLag>
            <PredecessorUID>41</PredecessorUID>
            <Type>1</Type>
        </PredecessorLink>
        <Rollup>0</Rollup>
        <Start>2019-02-11T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>45</UID>
        <WBS>1.4.1.5</WBS>
        <Work>P2DT0H0M0S</Work>
    </Task>
    <Task>
        <CalendarUID>174</CalendarUID>
        <ConstraintDate/>
        <ConstraintType/>
        <Deadline/>
        <Duration>PT0H0M0S</Duration>
        <DurationFormat>7</DurationFormat>
        <EffortDriven>0</EffortDriven>
        <Estimated>0</Estimated>
        <Finish>2019-02-02T00:00:00</Finish>
        <Manual>0</Manual>
        <ManualDuration>PT0H0M0S</ManualDuration>
        <ManualFinish>2019-02-02T00:00:00</ManualFinish>
        <ManualStart>2019-02-02T00:00:00</ManualStart>
        <Milestone>1</Milestone>
        <Name>Make backup</Name>
        <ProjectExternallyEdited>0</ProjectExternallyEdited>
        <OutlineLevel>4</OutlineLevel>
        <OutlineNumber>1.4.1.6</OutlineNumber>
        <PercentComplete>0</PercentComplete>
        <Rollup>1</Rollup>
        <Start>2019-02-02T00:00:00</Start>
        <Summary>0</Summary>
        <Type>0</Type>
        <UID>46</UID>
        <WBS>1.4.1.6</WBS>
        <Work>PT0H0M0S</Work>
    </Task>

    
    
    
    

    
    
    
    
    • Edited by fabiojpoli Friday, October 16, 2020 11:39 AM
    Friday, October 16, 2020 11:35 AM
  • John or Tom, do you have MS Project 2016 version to import my whole xml above and send me a screenshot please to me know if works for that version? Thank you
    
    
    
    
    Friday, October 16, 2020 1:19 PM
  • fabiojpoli,

    Sorry I do not have Project 2016.

    John

    Friday, October 16, 2020 3:30 PM
  • Now I removed another data and I have the minimum perfect test case.

       

    The problems I have only on duration, start and finish dates. I don't understand why MS Project changes the values if on XML is correct. Bellow the XML with correct values and screenshot of the project imported with wrong values. What is the problem?

    For example, on the XML, the task “configure port” is with this data:

    <Name>Configure ports</Name>
      <Duration>P2DT0H0M0S</Duration> 
      <Start>2019-01-14T00:00:00</Start>  
      <Finish>2019-01-16T00:00:00</Finish>

    But the image show the xml I imported the MS Project converted it to:

        duration: 0 days
        start: 2019-01-14
        finish: 2019-01-14



    XML: 

    <?xml version="1.0" encoding="UTF-8" standalone="yes"?>
    <Project
        xmlns="http://schemas.microsoft.com/project">
        <CalendarUID>174</CalendarUID>
        <CreationDate>2020-10-16T11:49:26</CreationDate>
        <CurrentDate>2020-10-16T11:49:26</CurrentDate>
        <DaysPerMonth>20</DaysPerMonth>
        <FinishDate>2019-02-08T00:00:00</FinishDate>
        <MinutesPerDay>1440</MinutesPerDay>
        <MinutesPerWeek>7200</MinutesPerWeek>
        <Name>Gantt</Name>
        <SaveVersion>14</SaveVersion>
        <ScheduleFromStart>1</ScheduleFromStart>
        <StartDate>2019-01-14T00:00:00</StartDate>
        <Title>Gantt</Title>
        <WorkFormat>2</WorkFormat>
        <Calendars>
            <Calendar>
                <BaseCalendarUID>-1</BaseCalendarUID>
                <IsBaseCalendar>1</IsBaseCalendar>
                <Name>General - imported</Name>
                <UID>174</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
            <Calendar>
                <BaseCalendarUID>174</BaseCalendarUID>
                <IsBaseCalendar>0</IsBaseCalendar>
                <Name>Business - imported</Name>
                <UID>175</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
            <Calendar>
                <BaseCalendarUID>174</BaseCalendarUID>
                <IsBaseCalendar>0</IsBaseCalendar>
                <Name>Night shift - imported</Name>
                <UID>178</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
        </Calendars>
        <Tasks>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P19DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P19DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Launch SaaS Product</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>1</OutlineLevel>
                <OutlineNumber>1</OutlineNumber>
                <PercentComplete>14</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>1000</UID>
                <WBS>1</WBS>
                <Work>P1M10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P2DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-16T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P2DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-16T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Setup web server</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.1</OutlineNumber>
                <PercentComplete>50</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>1</UID>
                <WBS>1.1</WBS>
                <Work>P2DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P2DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-16T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P2DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-16T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Configure ports</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.1.1</OutlineNumber>
                <PercentComplete>50</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>14</UID>
                <WBS>1.1.1</WBS>
                <Work>P2DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P15DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P15DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Setup Test Strategy</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.2</OutlineNumber>
                <PercentComplete>15</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>3</UID>
                <WBS>1.2</WBS>
                <Work>P1M1DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P5DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-19T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P5DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-19T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Hire QA staff</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.2.1</OutlineNumber>
                <PercentComplete>40</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>31</UID>
                <WBS>1.2.1</WBS>
                <Work>P5DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Write test specs</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.2.2</OutlineNumber>
                <PercentComplete>10</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>33</UID>
                <WBS>1.2.2</WBS>
                <Work>P26DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Unit tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.1</OutlineNumber>
                <PercentComplete>20</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>331</UID>
                <WBS>1.2.2.1</WBS>
                <Work>P10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P5DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-26T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P5DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-26T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>UI unit tests / individual screens</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.2</OutlineNumber>
                <PercentComplete>10</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>332</UID>
                <WBS>1.2.2.2</WBS>
                <Work>P5DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Application tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>333</UID>
                <WBS>1.2.2.3</WBS>
                <Work>P10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P1DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-22T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P1DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-22T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Monkey tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.4</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>334</UID>
                <WBS>1.2.2.4</WBS>
                <Work>P1DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Application Implementation</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>3</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>4</UID>
                <WBS>1.3</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Phase #1</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.3.1</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>400</UID>
                <WBS>1.3.1</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-04T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Implement role based access</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.1</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-04T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>43</UID>
                <WBS>1.3.1.1</WBS>
                <Work>P4DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P3DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-07T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P3DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-07T00:00:00</ManualFinish>
                <ManualStart>2019-02-04T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Basic test coverage</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.2</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-04T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>44</UID>
                <WBS>1.3.1.2</WBS>
                <Work>P3DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>PT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>PT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>1</Milestone>
                <Name>Make backup</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>46</UID>
                <WBS>1.3.1.3</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
        </Tasks>
        <Resources></Resources>
        <Assignments></Assignments>
    </Project>

    Friday, October 16, 2020 4:25 PM
  • Fixed the problem.

    To work is required to add the field "RemainingDuration" to the tasks and (as suggested by Tom) change the format to hours from days to hours. Even microsoft doc suppose to format duration like P2DT1H0M for 2 days 1 hour but the correct they support is only in days PT25H0M for 2 days and 1 hour.

    Thank you!

    • Marked as answer by fabiojpoli Monday, October 19, 2020 6:12 PM
    Monday, October 19, 2020 6:12 PM