Hi lisayakir,
First create a resource.
Then create a task with 5 days duration.
Then enter the task details. Goto Resources tab. Select the resource mentioned at first step. Assign %20 units.
I hope that helps,
For Project questions, you should better use http://social.msdn.microsoft.com/Forums/en-US/projectprofessional2010general/threads