change working time with project professional 2010 RRS feed

  • Question

  • Hi!

    I want change the working time in Project Professional 2010 for a specific resource in a specific project, because I want test the effect of the insert of the holiday.

    I doing:

    1. I open a existing project
    2. I click on "Change Working Time" and select from "For calendar" the resource
    3. I can't modify the calendar and insert exception day

    I also doing:

    • I open "resource sheet" view
    • I click the resource and click on "Change working time", but I can't modify the calendar

    If I create a new project, I can modify the calendar of resources.

    Can you help me?

    Thank you!

    Samantha

    Thursday, September 23, 2010 1:49 PM

Answers

  • Samantha --
     
    The default settings in Project Server 2010 only allow the Project Server administrator to change the calendars of enterprise resources in the Enterprise Resource Pool.  So, you cannot do what you are trying to do in an enterprise project for an enterprise resource.  This means you should contact your Project Server administrator about this issue.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, September 23, 2010 2:54 PM

All replies

  • Samantha --
     
    The default settings in Project Server 2010 only allow the Project Server administrator to change the calendars of enterprise resources in the Enterprise Resource Pool.  So, you cannot do what you are trying to do in an enterprise project for an enterprise resource.  This means you should contact your Project Server administrator about this issue.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, September 23, 2010 2:54 PM
  • Thank's.

    But I am an administrator and can't modify the resource calendar for single project. So, do I must modify the calendar for all projects in Project Server using the Resource Center and not anly for the single project and temporally?

    Thank's! 

    Thursday, September 23, 2010 3:46 PM
  • Samantha --
     
    As the Project Server administrator, you cannot edit the resource information for a resource for only one project.  If you make changes to an enterprise resource, such as adding vacation time on the resource's calendar, this change affects every project to which the resource is assigned tasks.  Hope this helps.  Hope this clarification helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, September 23, 2010 5:54 PM
  • It is clear!

    Thank's, Dale!

    Friday, September 24, 2010 7:45 AM
  • Samantha --
     
    You are more than welcome, my friend!

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, September 24, 2010 12:27 PM