  • Hi, in Resource Center can I create a custom view to filter Resource Availability by a Project Custom field or am I stuck with the 4 out of the box views ie Assignment work by Resource, Assignment work by Project etc?

    thanks

    Steve

    Wednesday, July 8, 2015 6:40 PM

Answers

  • Stev Scott42 --

    Bad news, my friend.  You are limited to the four default views on the Resource Availability page.  It is not possible to create custom views on this page.  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by Stev Scott42 Wednesday, July 8, 2015 7:51 PM
    Wednesday, July 8, 2015 7:42 PM

All replies

  • Stev Scott42 --

    Bad news, my friend.  You are limited to the four default views on the Resource Availability page.  It is not possible to create custom views on this page.  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by Stev Scott42 Wednesday, July 8, 2015 7:51 PM
    Wednesday, July 8, 2015 7:42 PM
  • thanks for confirming Dale

    rgds

    Steve

    Wednesday, July 8, 2015 7:51 PM
  • Steve --

    You are more than welcome for the help, my friend!  :)