Hi,
What is the use of the Project Site Settings - Regional Settings while the calendars are defined at the enterprise level?
Thanks
Saturday, January 29, 2011 9:32 PM
Answers
-
Hi WLID1966,
These regional settings are specific to the Project site level, and are not in sync with the Enterprise Project Calendar by any means.
The settings you will change here will effect your Project site calendar settings, for instance if you can change the Week start day and then browse your project site calendar you will witness the change. Same goes for the Start tiem and End time, change the time and verify the change in the calendar.
You can avail these options,
1: to sync you site calendar with your outlook calendar settings
2: if your project team follows the different work days/time for this project, you can modify the project site date/time with the same settings so that project schedule and project site stays at the same calendar level.
Hope this help you clear your thoughts.
| Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |- Marked as answer by WLID1966 Sunday, January 30, 2011 8:38 AM
Sunday, January 30, 2011 8:29 AM
All replies
-
Hi,
The Regional Settings within the Project Site define things like the date format and currency symbol used in the project site lists, they are separate from the enterprise calendars which define working / non working days inside the project schedules.
Hope this makes sense,
Alex Burton
www.epmsource.com | Twitter
Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page- Proposed as answer by Alexander.Burton Sunday, January 30, 2011 2:52 AM
Sunday, January 30, 2011 2:52 AM -
Thanks Alex,
But there are also "Define your work week", Start Time, End Time... what hapens if these settings at project site level are in contradiction with the Enterprise Settings?
Sunday, January 30, 2011 8:07 AM -
Hi WLID1966,
These regional settings are specific to the Project site level, and are not in sync with the Enterprise Project Calendar by any means.
The settings you will change here will effect your Project site calendar settings, for instance if you can change the Week start day and then browse your project site calendar you will witness the change. Same goes for the Start tiem and End time, change the time and verify the change in the calendar.
You can avail these options,
1: to sync you site calendar with your outlook calendar settings
2: if your project team follows the different work days/time for this project, you can modify the project site date/time with the same settings so that project schedule and project site stays at the same calendar level.
Hope this help you clear your thoughts.
| Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |- Marked as answer by WLID1966 Sunday, January 30, 2011 8:38 AM