MS project calendars RRS feed

  • Question

  • I am using MS project 2013. i have set up the project with a 24hr calendar. i have set up a number of resources with their specific calendars. I have set up the resource availability for the project.

    When I assign resources to a task the applicable resource calendar does not show as selected/applied in the task information/advanced table. Is that normal?

    The resource calendar does not adjust the task calendar and it does not adjust the time line when i assign resources. 

    To have the resource calendar supersede/override the Project Calendar do i have to change each activity in the task information/advanced table. this is time consuming and frustrating in that i think it is a step should not be required.