Answered by:
Is there any way to get the latest baseline start date directly?

Question
-
Hi,
Is there any way to get the latest baseline start date directly?
Thanks in advance!
Anuranjan Prasad
Monday, September 5, 2011 12:16 PM
Answers
-
Hi Sunil Sir,
Actully we are calculating some budget value which will be displayed on the PDP page and that is getting calculated from latest baseline cost .
So better though to create one project level custom filed(Formula Based) and display it on PDP page.
I think i have explained enough if you required anything else in this please revert.
Tx in Advance
Vipin Upadhyay
Vipin Upadhyay AonHewitt- Marked as answer by Anuranjan Prasad Tuesday, September 13, 2011 3:14 AM
Friday, September 9, 2011 11:00 AM -
Hi All,
Create a custom field with entity type as 'Project', Type 'date' and paste the below mentioned formula. This works for me :)
IIf(Not IsNull([Baseline9 Finish]), [Baseline9 Finish], IIf(Not IsNull([Baseline8 Finish]), [Baseline8 Finish], IIf(Not IsNull([Baseline7 Finish]), [Baseline7 Finish], IIf(Not IsNull([Baseline6 Finish]), [Baseline6 Finish], IIf(Not IsNull([Baseline5 Finish]), [Baseline5 Finish], IIf(Not IsNull([Baseline4 Finish]), [Baseline4 Finish], IIf(Not IsNull([Baseline3 Finish]), [Baseline3 Finish], IIf(Not IsNull([Baseline2 Finish]), [Baseline2 Finish], IIf(Not IsNull([Baseline1 Finish]), [Baseline1 Finish], IIf(Not IsNull([Baseline Finish]), [Baseline Finish], ""))))))))))
Thanks
Anuranjan Prasad
- Proposed as answer by Vipin Upadhyay Monday, September 12, 2011 3:21 PM
- Marked as answer by Anuranjan Prasad Tuesday, September 13, 2011 3:14 AM
Monday, September 12, 2011 1:32 PM
All replies
-
hi there,
You can get this from the PWA Reporting database for the Project Baseline information look in the MSP_EPMProject_Userview or for the task baseline data look in the MSP_EPMTask_Userview.
Hope this helps.
Thanks
Paul
Paul Mather | Twitter | http://pwmather.wordpress.comMonday, September 5, 2011 12:20 PM -
Hi Anuranjan,
in the scope of Project Client and within a single project plan you can group your tasks using a field like "Baseline Start1".
Best Regards
Philipp
Monday, September 5, 2011 12:29 PM -
Hi ,
Is there any way we can get this by formula on PDP pages
Vipin Upadhyay AonHewittTuesday, September 6, 2011 9:22 AM -
Hi Vipin
Why do you need it using formula on PDP, could you elaborate a more on the requirement ?
Thanks | Sunil Kr Singh | http://epmxperts.wordpress.comTuesday, September 6, 2011 9:37 AM -
Hi Sunil Sir,
Actully we are calculating some budget value which will be displayed on the PDP page and that is getting calculated from latest baseline cost .
So better though to create one project level custom filed(Formula Based) and display it on PDP page.
I think i have explained enough if you required anything else in this please revert.
Tx in Advance
Vipin Upadhyay
Vipin Upadhyay AonHewitt- Marked as answer by Anuranjan Prasad Tuesday, September 13, 2011 3:14 AM
Friday, September 9, 2011 11:00 AM -
Still not sure I follow, but if properly done, the Last Saved Baseline shouldalways be Baseline0, with each Baseline saved also to Baseline1/2/3/x forposterity.So you can pull the Baseline0 Finish date for a specific task and that shouldalways be the last one.If you just want to roll up the latest Baseline Finish date in a collectionof tasks, I would create a custom Date field with the formula =[BaselineFinish], then set it to Rollup to summary bars as the Maximum. On the Projectlevel, create a new Project level date field with the formula "=[Date]" where[Date] is the first field you created.
Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinskyFriday, September 9, 2011 1:53 PM -
Hi All,
Create a custom field with entity type as 'Project', Type 'date' and paste the below mentioned formula. This works for me :)
IIf(Not IsNull([Baseline9 Finish]), [Baseline9 Finish], IIf(Not IsNull([Baseline8 Finish]), [Baseline8 Finish], IIf(Not IsNull([Baseline7 Finish]), [Baseline7 Finish], IIf(Not IsNull([Baseline6 Finish]), [Baseline6 Finish], IIf(Not IsNull([Baseline5 Finish]), [Baseline5 Finish], IIf(Not IsNull([Baseline4 Finish]), [Baseline4 Finish], IIf(Not IsNull([Baseline3 Finish]), [Baseline3 Finish], IIf(Not IsNull([Baseline2 Finish]), [Baseline2 Finish], IIf(Not IsNull([Baseline1 Finish]), [Baseline1 Finish], IIf(Not IsNull([Baseline Finish]), [Baseline Finish], ""))))))))))
Thanks
Anuranjan Prasad
- Proposed as answer by Vipin Upadhyay Monday, September 12, 2011 3:21 PM
- Marked as answer by Anuranjan Prasad Tuesday, September 13, 2011 3:14 AM
Monday, September 12, 2011 1:32 PM