Answered by:
How to manage time and task progress in pwa 2010

Question
-
hello,
I would like to distinguish time and task tracking like said technet :
http://technet.microsoft.com/en-gb/library/gg597642.aspx.
When i have a task with 20 hours, I can finish it in 15 hours or in 25 hours but i don't know how do this.
How can I keep the initial time (20 hours) and the time passed (15 or 25 hours) then closed the task ?
Thanks.
Monday, January 30, 2012 9:50 AM
Answers
-
Bobosh,
The "planned" values will change with actuals. That's how project works, so that it can recalculate the dates/durations/work and provide you data that you can analyze.
If you need comparison with your initial planned work/dates, you need to save it as a baseline. Then you will have a snapshot that you can compare against.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com- Proposed as answer by Christophe FiessingerMicrosoft employee Monday, January 30, 2012 5:24 PM
- Marked as answer by Prasanna AdaviMVP Wednesday, March 11, 2015 6:32 PM
Monday, January 30, 2012 4:58 PM
All replies
-
Hi,
You have to use Timesheet to manage your Actual Time and Planned time. Please find the link below that describe the usage of timesheets
http://blogs.msdn.com/b/project/archive/2009/11/23/time-tracking-in-project-server-2010.aspx
Hope this will help.
_________ Fahad Ahmed Khan .NET Articles, Web Development, SharePoint and Project Server Custom Solution ProviderMonday, January 30, 2012 10:19 AM -
I've already read those articles but it didn't help me.
When I used timesheet and added hours to a task, if I work more than planned on the task, the time of task grow too.
So, I can't compare between actual time and time planned.
Monday, January 30, 2012 2:37 PM -
Bobosh,
The "planned" values will change with actuals. That's how project works, so that it can recalculate the dates/durations/work and provide you data that you can analyze.
If you need comparison with your initial planned work/dates, you need to save it as a baseline. Then you will have a snapshot that you can compare against.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com- Proposed as answer by Christophe FiessingerMicrosoft employee Monday, January 30, 2012 5:24 PM
- Marked as answer by Prasanna AdaviMVP Wednesday, March 11, 2015 6:32 PM
Monday, January 30, 2012 4:58 PM