  • Is there a way I can use different units for a tiers in the same Gantt chart? For example,  if the bottom tier is in Hours, can I make it to show in days later on (say in the month of September). I assume, there is no direct way. If there is any work-around , let me know. Thanks

    Ulhas Samant

    Monday, July 27, 2015 11:34 AM

Answers

  • Hi,

    No you cannot do that. If you specify a given unit for a tiers, it applies for the entire tiers.

    A workaround would be to recoard a macro using the "developer" tab from the ribbon and associate the macro to a button, so you can switch a tiers from a unit to another just by clicking on the button.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by banda_india Saturday, November 14, 2015 1:20 PM