How project health indicators can be created in project server 2010 PWA? RRS feed

  • Question

  • Hi,

    I have seen in microsoft demo that project health indicators(red, green and yellow) are available in a view in project center. please guide me on how to create project health indicators.

    Thanks,

    Lovely


    Lovely
    Tuesday, December 14, 2010 10:06 AM

Answers

  • Hi Lovely

    Its pretty much easy to create an indicator, Steps would be

    Goto Server Settings >> Enterprise Custom Field >> Create a Custom field  >> New Field >> project level field for Project Centre >> In the custom attribute >> choose Formula (though for diplaying indicator can be based on text / number / cost field, but typically most of the time we use it with formula)  >> Create a Formula such as

    Switch(Len(CStr([Baseline Finish])) < 3, "No baseline",
    ([Cost] + 1) / ([Baseline Cost] + 1) > 1.2, "Overbudget by 20% or more",
    ([Cost] + 1) / ([Baseline Cost] + 1) > 1, "Overbudget",
    True, "Under budget")

    Now Scroll below to "Values to Display Section" Select Graphical indicators >> put your criteria such as "Equals", Values field should contain the actual value i.e. output of formula,   "No Baseline" (text should be exactly the same as it would be in your formula output)   
     

    In the image column clicking would pull a dropdown, just select the image you would like to display for corresponding value, repeat the test, value for each output you anticipate as  a result of formula, save it once done

    Now include this custom field in any of your relevant views, and you are good to go

    Note ::  after creating the formula custom field, do remeber to recalculate your project by opening in MSP and save followed by a publish :)

    For more reference, refer to http://msdn.microsoft.com/en-us/library/ee767700.aspx

     

     


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com