MS Project - XML imported with wrong duration, Start and Finish dates RRS feed

  • Question

  • I have created a XML file to import to MS Project 2019 using Javascript.

    The problems I have only on duration, start and finish dates. I don't understand why MS Project changes the values if on XML is correct. Bellow the XML with correct values and screenshot of the project imported with wrong values. What is the problem?

    For example, on the XML, the task “configure port” is with this data:

    <Name>Configure ports</Name>
    <Duration>P2DT0H0M0S</Duration>
    <Start>2019-01-14T00:00:00</Start>
    <Finish>2019-01-16T00:00:00</Finish>

    But the image show the xml I imported the MS Project converted it to:

    duration: 0 days
    start: 2019-01-14
    finish: 2019-01-14
    

    XML: 

    <?xml version="1.0" encoding="UTF-8" standalone="yes"?>
    <Project
        xmlns="http://schemas.microsoft.com/project">
        <CalendarUID>174</CalendarUID>
        <CreationDate>2020-10-16T11:49:26</CreationDate>
        <CurrentDate>2020-10-16T11:49:26</CurrentDate>
        <DaysPerMonth>20</DaysPerMonth>
        <FinishDate>2019-02-08T00:00:00</FinishDate>
        <MinutesPerDay>1440</MinutesPerDay>
        <MinutesPerWeek>7200</MinutesPerWeek>
        <Name>Gantt</Name>
        <SaveVersion>14</SaveVersion>
        <ScheduleFromStart>1</ScheduleFromStart>
        <StartDate>2019-01-14T00:00:00</StartDate>
        <Title>Gantt</Title>
        <WorkFormat>2</WorkFormat>
        <Calendars>
            <Calendar>
                <BaseCalendarUID>-1</BaseCalendarUID>
                <IsBaseCalendar>1</IsBaseCalendar>
                <Name>General - imported</Name>
                <UID>174</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
            <Calendar>
                <BaseCalendarUID>174</BaseCalendarUID>
                <IsBaseCalendar>0</IsBaseCalendar>
                <Name>Business - imported</Name>
                <UID>175</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>08:00:00</FromTime>
                                <ToTime>12:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>13:00:00</FromTime>
                                <ToTime>17:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
            <Calendar>
                <BaseCalendarUID>174</BaseCalendarUID>
                <IsBaseCalendar>0</IsBaseCalendar>
                <Name>Night shift - imported</Name>
                <UID>178</UID>
                <WeekDays>
                    <WeekDay>
                        <DayType>1</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                    <WeekDay>
                        <DayType>2</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>3</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>4</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>5</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>6</DayType>
                        <DayWorking>1</DayWorking>
                        <WorkingTimes>
                            <WorkingTime>
                                <FromTime>00:00:00</FromTime>
                                <ToTime>06:00:00</ToTime>
                            </WorkingTime>
                            <WorkingTime>
                                <FromTime>22:00:00</FromTime>
                                <ToTime>00:00:00</ToTime>
                            </WorkingTime>
                        </WorkingTimes>
                    </WeekDay>
                    <WeekDay>
                        <DayType>7</DayType>
                        <DayWorking>0</DayWorking>
                    </WeekDay>
                </WeekDays>
            </Calendar>
        </Calendars>
        <Tasks>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P19DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P19DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Launch SaaS Product</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>1</OutlineLevel>
                <OutlineNumber>1</OutlineNumber>
                <PercentComplete>14</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>1000</UID>
                <WBS>1</WBS>
                <Work>P1M10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P2DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-16T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P2DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-16T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Setup web server</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.1</OutlineNumber>
                <PercentComplete>50</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>1</UID>
                <WBS>1.1</WBS>
                <Work>P2DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P2DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-16T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P2DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-16T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Configure ports</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.1.1</OutlineNumber>
                <PercentComplete>50</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>14</UID>
                <WBS>1.1.1</WBS>
                <Work>P2DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P15DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P15DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Setup Test Strategy</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.2</OutlineNumber>
                <PercentComplete>15</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>3</UID>
                <WBS>1.2</WBS>
                <Work>P1M1DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P5DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-19T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P5DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-19T00:00:00</ManualFinish>
                <ManualStart>2019-01-14T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Hire QA staff</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.2.1</OutlineNumber>
                <PercentComplete>40</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-14T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>31</UID>
                <WBS>1.2.1</WBS>
                <Work>P5DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Write test specs</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.2.2</OutlineNumber>
                <PercentComplete>10</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>33</UID>
                <WBS>1.2.2</WBS>
                <Work>P26DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Unit tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.1</OutlineNumber>
                <PercentComplete>20</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>331</UID>
                <WBS>1.2.2.1</WBS>
                <Work>P10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P5DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-26T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P5DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-26T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>UI unit tests / individual screens</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.2</OutlineNumber>
                <PercentComplete>10</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>332</UID>
                <WBS>1.2.2.2</WBS>
                <Work>P5DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P10DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P10DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Application tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>333</UID>
                <WBS>1.2.2.3</WBS>
                <Work>P10DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P1DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-01-22T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P1DT0H0M0S</ManualDuration>
                <ManualFinish>2019-01-22T00:00:00</ManualFinish>
                <ManualStart>2019-01-21T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Monkey tests</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.2.2.4</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>31</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-01-21T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>334</UID>
                <WBS>1.2.2.4</WBS>
                <Work>P1DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Application Implementation</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>2</OutlineLevel>
                <OutlineNumber>1.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <PredecessorLink>
                    <LagFormat>7</LagFormat>
                    <LinkLag>0</LinkLag>
                    <PredecessorUID>3</PredecessorUID>
                    <Type>1</Type>
                </PredecessorLink>
                <Rollup>0</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>4</UID>
                <WBS>1.3</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Phase #1</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>3</OutlineLevel>
                <OutlineNumber>1.3.1</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>1</Summary>
                <Type>1</Type>
                <UID>400</UID>
                <WBS>1.3.1</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P4DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-08T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P4DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-08T00:00:00</ManualFinish>
                <ManualStart>2019-02-04T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Implement role based access</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.1</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-04T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>43</UID>
                <WBS>1.3.1.1</WBS>
                <Work>P4DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>P3DT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-07T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>P3DT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-07T00:00:00</ManualFinish>
                <ManualStart>2019-02-04T00:00:00</ManualStart>
                <Milestone>0</Milestone>
                <Name>Basic test coverage</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.2</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>0</Rollup>
                <Start>2019-02-04T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>44</UID>
                <WBS>1.3.1.2</WBS>
                <Work>P3DT0H0M0S</Work>
            </Task>
            <Task>
                <CalendarUID>174</CalendarUID>
                <ConstraintDate/>
                <ConstraintType/>
                <Deadline/>
                <Duration>PT0H0M0S</Duration>
                <DurationFormat>7</DurationFormat>
                <EffortDriven>0</EffortDriven>
                <Estimated>0</Estimated>
                <Finish>2019-02-02T00:00:00</Finish>
                <Manual>0</Manual>
                <ManualDuration>PT0H0M0S</ManualDuration>
                <ManualFinish>2019-02-02T00:00:00</ManualFinish>
                <ManualStart>2019-02-02T00:00:00</ManualStart>
                <Milestone>1</Milestone>
                <Name>Make backup</Name>
                <ProjectExternallyEdited>0</ProjectExternallyEdited>
                <OutlineLevel>4</OutlineLevel>
                <OutlineNumber>1.3.1.3</OutlineNumber>
                <PercentComplete>0</PercentComplete>
                <Rollup>1</Rollup>
                <Start>2019-02-02T00:00:00</Start>
                <Summary>0</Summary>
                <Type>0</Type>
                <UID>46</UID>
                <WBS>1.3.1.3</WBS>
                <Work>PT0H0M0S</Work>
            </Task>
        </Tasks>
        <Resources></Resources>
        <Assignments></Assignments>
    </Project>

    Friday, October 16, 2020 4:30 PM

Answers

  • Fixed the problem.

    To work is required to add the field "RemainingDuration" to the tasks and change the format to hours from days to hours. Even microsoft doc to suppose to format duration like P2DT1H0M for 2 days 1 hour but the correct they support is only in days PT25H0M for 2 days and 1 hour.

    Thank you!