Billed Hours vs Actual Hours RRS feed

  • Question

  • My customer (a services company) stumped me with the following question:  They are deploying P2010

    How do we use timesheets to capture non-billable hours.  Lets say for example Joe billed 100 hours to create Document A, but he actually worked 120 hours.   can we distinguish those on a task by task basis??

    Thursday, September 23, 2010 8:13 PM

Answers

  • Hi JohnBGood,

    The Timesheet feature of Project Server 2010 allows for both billable and non-billable time tracking.

    • In Project Web App, go to Server Settings -> Timesheet Settings and Defaults
    • Make sure the option 'The timesheet will use standard Overtime and Non-Billable time tracking' is selected and save the settings

    On the timesheet, the user can now select the option 'Non-Billable' on the ribbon. This will display the Actual Non-Billable row for each task, in which they can enter non-billable time.

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    Thursday, September 23, 2010 8:25 PM

All replies

  • Hi JohnBGood,

    The Timesheet feature of Project Server 2010 allows for both billable and non-billable time tracking.

    • In Project Web App, go to Server Settings -> Timesheet Settings and Defaults
    • Make sure the option 'The timesheet will use standard Overtime and Non-Billable time tracking' is selected and save the settings

    On the timesheet, the user can now select the option 'Non-Billable' on the ribbon. This will display the Actual Non-Billable row for each task, in which they can enter non-billable time.

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    Thursday, September 23, 2010 8:25 PM
  • Great!!!...

     

    Just to confirm... I can enter billlable and non- billable time on at task by task basis per resource - YES??

     

     

    Thursday, September 23, 2010 8:57 PM
  • Yes!
    My EPM blog: Projectopolis
    Thursday, September 23, 2010 9:10 PM