Hi All
We have a situation, using Project Server 2007, where the rates dsiplayed in Resource Center is incorrect. Resource rates are adjusted each year, so in this scenario the resources have 4 rates (with effective dates) in the cost rate table. In resource center
however, the standard and overtime rate displayed is for the 2nd rate change as apposed to the third one (the fourth rate's effective date is still in the future). When opening the resource in MSP or assigning the Resource to tasks in MSP the currents standard
and overtime rate used is correct, it just shows the wrong one in Resource Center. Has anyone seen this before and possibly know of a 'fix' for this?
Regards
Coenraad Swanepoel