locked
Resource Rates in Resource Center RRS feed

  • Question

  • Hi All

    We have a situation, using Project Server 2007, where the rates dsiplayed in Resource Center is incorrect. Resource rates are adjusted each year, so in this scenario the resources have 4 rates (with effective dates) in the cost rate table. In resource center however, the standard and overtime rate displayed is for the 2nd rate change as apposed to the third one (the fourth rate's effective date is still in the future). When opening the resource in MSP or assigning the Resource to tasks in MSP the currents standard and overtime rate used is correct, it just shows the wrong one in Resource Center. Has anyone seen this before and possibly know of a 'fix' for this?

    Regards

    Coenraad Swanepoel

    Thursday, November 25, 2010 6:28 AM

Answers

  • Hi Coenraad,

    no idea if it a good answer for you? ;-)
    I can't reproduce with SP2 + CU October 2010.

    Regards
    Barbara

    Thursday, November 25, 2010 6:49 AM

All replies

  • Hi Coenraad,

    no idea if it a good answer for you? ;-)
    I can't reproduce with SP2 + CU October 2010.

    Regards
    Barbara

    Thursday, November 25, 2010 6:49 AM
  • Thanks Barbara.

    Am at the client now, but the problem is now 'fixed'. They have integration to update their resource pool, so I think there was just a delay on the refresh of the RDB. Thanks for the testing.

    Regards

    Coenraad Swanepoel

     

    Tuesday, November 30, 2010 8:28 AM
  • Great to read!

    Barbara

    Tuesday, November 30, 2010 8:31 AM