In Project Server 2007, do tasks show on a resources timesheet until the the tasks is complete? RRS feed

  • Question

  • In Project Server 2007, do tasks show on a resources timesheet until the the tasks is complete or do they drop off at some point.
    Friday, July 16, 2010 5:16 PM

Answers

  • Dressage Rider --
     
    In Project Server 2007, completed tasks behave as follows:
    • If the user has the All Tasks option selected on the My Tasks page, the completed tasks never disappear.
    • If the user has the Current Tasks option selected, the completed tasks disappear when they hit the "Current task" window defined by the Project Server administrator.  By default, this value is 10 days unless the administrator changes it.
    Hope this helps.
    In Project Server 2007, do tasks show on a resources timesheet until the the tasks is complete or do they drop off at some point.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, July 16, 2010 5:50 PM