Task Start date and End date update on the basis of Actual Start and End date RRS feed

  • Question

  • Hello Friends,

    I am facing an little issue... i have assign 3 tasks to user...

    Task name     Start                Finish

    Test               20/02/2012     22/02/2012

    Test1             23/02/2012     27/02/2012

    Now the issue is if user start the second task first and in tasks add his working hours and PM approves it then the start date is automatically changed... we dont want to do this happend because its change the track record of project. Please help. Thanks


    Hammad Umar

    Wednesday, February 22, 2012 6:05 AM