I reported the following main steps to describe my doubt:
1. task resources update %work complete (the actual work is automatically calculated) via task :
2. task resources update timesheet actual work with the effective work spent on task in a day:
My project online settings predict that the resources communicate the percentage of completion of the work, with values between 0 and 100%
After the approval cycle, the actual time of timesheet is still different from that one of the task (linked to %work complete). I would expect to see the same value. Is it correct?