locked
Clearing the queue from old failed events RRS feed

  • Question

  • Hello,

    is there any way to clear old queue jobs which have status "failed" and "cancelled" in Project Server 2013?

    Thank you.

    Monday, April 14, 2014 10:28 AM

Answers

  • Hello,

    They will clear after 7 days if you have the default queue settings. Check the "Cleanup Age Limit For Non-Successful Jobs (in hours)" value on the "Manage Queue Settings for Project Web App" in Central Admin on the Project Service Application.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Monday, April 14, 2014 1:39 PM

All replies

  • Hello,

    They will clear after 7 days if you have the default queue settings. Check the "Cleanup Age Limit For Non-Successful Jobs (in hours)" value on the "Manage Queue Settings for Project Web App" in Central Admin on the Project Service Application.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Monday, April 14, 2014 1:39 PM
  • Hello Paul, 

    When I go into the "Manage Queue Jobs" as the admin guide says, I just get the the jobs in the queue with options to filter it. 

    What could be wrong? Is it a permission issue?

    Thanks.


    Hassan

    Tuesday, April 15, 2014 6:35 AM
  • Hello,

    You need to access it from Central Admin, not PWA. Click the "Manage Queue Settings for Project Web App" in Central Admin on the Project Service Application page.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Tuesday, April 15, 2014 8:21 AM
  • That's what I did.

    Here's what I get:


    Hassan

    Tuesday, April 15, 2014 8:25 AM
  • You don't click on Manage. Where you see the PWA instance, click the  "Manage Queue Settings for Project Web App" click above.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Tuesday, April 15, 2014 8:27 AM
  • Thank you Paul. I had it mixed up.


    Hassan