    In the Timesheet Settings and Default page (2010), the first settings were "Current task assignments" with "Allow top-level time reporting" desabled.

    Know, I'm asked to use Current project.

    Is it posssible to change the tracking level during the project life cycle?

    According my first test, it seems that doesn't work.

    Thanks

    Saturday, July 21, 2012 12:53 PM

Answers

  • It doesn't affect already created timesheets, only new timesheets. Try opening a timesheet for a future week once you change the setting.

    Also, if you are using Single Entry Mode, you typically don't want to log time at the Project level.