Project Server 2010: Resources Assigned Incorrectly to Fixed Duration Tasks RRS feed

  • Question

  • Good evening,

    In one of our work plans, we have a fixed duration task with a duration of 10 days.  When we assign a resource to the task, it assigns them for 1 day, not the expected 10 days.

    What causes this?  Am I not understanding how fixed duration tasks work?  I would think the assigned resource would be assigned for 10 days, not 1...

    Thanks in advance!

    Bryan

    Sunday, July 31, 2011 11:54 PM

Answers

  • Hi Bryan,

    I have just tried this and the resource is assigned as anticipated - for 10 days 8 hours per day.

    - I created the task

    - changed the task to fixed duration ( non effort driven)

    - craeted a resource

    - double clicked the tasks to get the task inforamtion and assigned the resource with 100%

    Does this happen to all your tasks?


    Marc Soester [MVP] http://marcsoester.blogspot.com
    • Marked as answer by epmXperts Monday, November 19, 2012 11:19 PM
    Monday, August 1, 2011 12:04 PM
  • Hi Bryan

    It has been long since this thread has been posted or updated, closing this thread assuming this has been already resolved, closing is necessary in order to keep the forum moderated

    please feel free to either reopen this thread or create a new one if you feel it has not been resolved & warrants further discussion

    Also would suggest if you find an answer or a workaround to this problem, please share in order for other forum members to get benefit of your experience


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    • Marked as answer by epmXperts Monday, November 19, 2012 11:20 PM
    Monday, November 19, 2012 11:20 PM

All replies

  • Bryan --

    How did you assign the resource to the task?  Did you use the Assign Resources dialog and then enter a Units value of 100%, for example?  Please give us more specifics about how you performed the assignment, as that would help us to trouble shoot your problem, and then we will try to help you. Let us know.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Monday, August 1, 2011 12:15 AM
  • Sure:

    • I used the Assign Resource dialogue and the default Units value was 100%. 
    • Only one resource was assigned.
    • The task is Fixed Duration
    • It isn't Effort Driven
    • It's not estimated duration
    • No deadline.
    • Constraint is ASAP
    • Earned value is % Complete
    • 1 Predecessor with a FS dependency
    • Auto-Scheduled

    Let me know if you need anything else.

    Thanks!

     

    Monday, August 1, 2011 12:22 AM
  • Hi Bryan,

    I have just tried this and the resource is assigned as anticipated - for 10 days 8 hours per day.

    - I created the task

    - changed the task to fixed duration ( non effort driven)

    - craeted a resource

    - double clicked the tasks to get the task inforamtion and assigned the resource with 100%

    Does this happen to all your tasks?


    Marc Soester [MVP] http://marcsoester.blogspot.com
    • Marked as answer by epmXperts Monday, November 19, 2012 11:19 PM
    Monday, August 1, 2011 12:04 PM
  • Hi Bryan

    It has been long since this thread has been posted or updated, closing this thread assuming this has been already resolved, closing is necessary in order to keep the forum moderated

    please feel free to either reopen this thread or create a new one if you feel it has not been resolved & warrants further discussion

    Also would suggest if you find an answer or a workaround to this problem, please share in order for other forum members to get benefit of your experience


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    • Marked as answer by epmXperts Monday, November 19, 2012 11:20 PM
    Monday, November 19, 2012 11:20 PM