none
Administrative task missing in timesheet in Project Server 2016 for some users RRS feed

  • Question

  • Hi,

    back in time (when Project Server 2010 was "current") same issue/question was registered. And there was a fix for that released by Microsoft.

    Our customer uses Project Server 2016 and the same issue is here. For some people (randomly) Timesheet is created without Administrative lines (Vacation and others). If we delete this Timesheet and create it again Administrative lines are back again.

    Not only users are random. Also there is no clue when it will happen. For some weeks Timesheet may be created with Administrative lines in place. Then one week without it. Or even several weeks in a row with those lines present. And then again without them.

    Any ideas what could be the reason? And how to "stop" this behavior?

    Regards,

    Vygantas


    Friday, November 8, 2019 6:18 PM