Rejected Task update still displays rejected start and finish values in my tasks RRS feed

  • Question

  • Hi, we are using PS 2007 and have noted that when a PM rejects an update the TM gets the rejected task notification (red cross) in my tasks. In this particular case the Team Member has proposed revised start and finish dates. If the PM rejects these there does not seem to be any way for the TM to see the original start and finish dates from PWA as the rejected dates still display until the TM resubmits a variation on these. BTW we are using %complete tracking not timephased actuals. Any ideas appreciated...
    Tuesday, September 14, 2010 11:00 PM

Answers