Any Problem Running Office 2010 SP2 with Project Server 2010 SP1? RRS feed

  • Question

  • We are running Project Server 2010 SP1 April 2013 CU and the desktop clients have now been upgraded to SP2 October 13 CU. We are having issues with projects in local cache showing as checked out when they are not actually checked out on the server. I was wondering if it is problematic to run the desktop client on a newer service pack than the server and if it could cause this type of issue?
    Wednesday, April 23, 2014 4:23 PM

Answers

  • Hello, Aaron.

    The answer is YES, you'll probably have some issues.

    I would recommend:

    • Downgrade clients to match Server's version
    • Upgrade Server to SP2+October '13 CU

    And my preferred:

    • Upgrade Server and clients to SP2 + '14 April CU
    • Proposed as answer by Justin Naughton Wednesday, April 23, 2014 5:08 PM
    • Marked as answer by Aaron Demenge Wednesday, April 23, 2014 5:37 PM
    Wednesday, April 23, 2014 4:58 PM