locked
Rejecting tasks in Project Server 2007 RRS feed

  • Question

  • Ok, please tell me if this is normal behavior for PS2007 sp2 june CU.

    Resource changes the finish date on a task, which causes the remaining to adjust then submits the update.  PM rejects the update. PM goes into Applied updates and errors page to publish project that contained the rejected update.  The my tasks page shows that the task was rejected, however the remaining hours and finish date does not recalcuate to what it was before the resource made updates.  I expected to see the task finish and remaining reflect what was in the project plan once it was rejected.  This did not happen even after the plan was published using project professional.  Is it possible to get the results I expected?

     

    Wednesday, October 6, 2010 8:52 PM

Answers

All replies