none
Project Server 2010 High Availability Scenario RRS feed

  • Question

  • Hello everyone

    I would like to know if it is possible to set up high availability scenario for Project Server 2010 environment. If it is possible how to accomplish this? The idea would be:

    • 2 Web Front Ends wih SharePoint 2010 Enterprise installed 
    • On each WFE Project Server installed and created Project Server Service Application

    Is this scenario possible?

    How to specify which server (Project server) handles requests regarding Projects and how to specify where is the secondary server. Is this scenario possible? Please explain or advise me different solution. Thanks

     

    Tuesday, May 10, 2011 7:57 PM

Answers

  • Hi Avion, if i understood correctly are you planning NLB for the both the servers (WEB and Application). this is very much possible for your high availability environment. But what about your database it needs to be also in NLB to make it complete high availability environment.

     


    Regards, Sujit - MCTS
    Wednesday, May 11, 2011 6:52 AM

All replies