locked
Resource Plan and Portfolio Analysis of resources (2013) RRS feed

  • Question

  • Hi,

    Is it possible to take account of the Resource Plans in a Portfolio Analysis of enterprise resources (Project Server 2013)

    Thanks


    • Edited by WLID1966 Friday, September 25, 2015 10:57 AM
    Friday, September 25, 2015 10:56 AM

Answers

  • Hi,

    Yes it is. Just be sure that the resource plans are configured for calculating the demand from the resource plan (or both from project plan and resource plan).


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by WLID1966 Friday, September 25, 2015 12:02 PM
    Friday, September 25, 2015 11:21 AM